FF&E installation is the last stage of a procurement programme and the one most exposed to everything that went before it. It is also short: a package that took nine months to specify and build is installed in days. Which is why an install either runs cleanly or becomes the most visible failure on the project.
Not when the construction programme says so — when the site is actually ready. The practical test is short and unforgiving:
Installing into a site that fails this list produces damaged furniture, protective wrap left on for weeks, and a snag list written against the installer for defects caused by the building.
Installs run room by room or floor by floor, in the order the site releases them, working away from the delivery point so finished rooms are never used as a route. On hospitality projects, guest rooms are typically installed as a repeated sequence — the first room is slow and becomes the reference standard; the rest run against it.
Public areas and F&B outlets go last: they are the routes everything else travels through, and the pieces are the largest and most exposed. See our restaurant furniture capability for how F&B outlets sequence within a property programme.
Furniture is unpacked at or near its final position, not at the loading bay. Every unpacked piece is inspected before placement, because a defect found in the carton is a claim and a defect found after placement is an argument.
Waste is the underrated line. A full-property FF&E package generates a genuinely large volume of crating, cardboard and film, and removing it is part of the install — not a problem handed to the site the following week.
Pieces are placed to the drawing, levelled on floors that are rarely as flat as they were specified, assembled where assembly was deferred for transport, and adjusted so doors and drawers align in situ. This is where an experienced install crew is worth its cost: the same package placed by a general labour crew reads subtly wrong in every room and no one can say why.
A snag list is written jointly, walked room by room: transit damage, finish defects, alignment, anything missing. Touch-ups happen on site; replacements are ordered against the same shop drawings the piece was built from, which is one more reason the drawings matter — see the FF&E procurement process.
Handover closes the package: signed snag list, remedial items scheduled, care and maintenance guidance for finishes, and warranty terms recorded against the pieces they cover.
The distinction is real. A freight crew delivers to a loading bay and leaves. An FF&E installation service takes the package from container to finished room — unpacking, inspection, placement, assembly, waste removal, snagging and handover — and carries responsibility for the condition of the piece when it is signed for.
We install what we build, coordinated by the same project team that manages production and logistics, which is what makes the snag list short and the accountability unambiguous. If FF&E as a scope is new to you, start with what FF&E covers.
Do you install the furniture you supply?
Yes. Delivery and installation are part of every project, coordinated by the same team that manages your shop drawings and production rather than subcontracted to a separate crew.
How long does an FF&E installation take?
Days rather than weeks for most packages, once the site is ready. The variable is site readiness and access, not the furniture.
What happens if a piece is damaged in transit?
It is identified at unpacking, before placement, and recorded on the snag list. Replacements are built against the original approved shop drawings so the finish matches the rest of the package.
Who removes the packaging waste?
We do. Crating, cardboard and film removal is part of the install rather than left for the site.
Can you install into an occupied or partially open property?
Yes — phased installs into live properties are sequenced around operations, with access routes and working hours agreed before delivery.